Wat Nakorn-In Project
Structures are standardized in order to reduce construction costs and time, using pre-cast segmental box girders with external pre-stressing. The major bridge across the Chao Phraya River is a pre-stressed concrete box girder constructed by the free cantilever method.
The project was split into five construction contracts. The first contract, including the bridge over Chao Phraya, started in the field in November 1999 and was completed in April 2002. Norconsult provided the Project Manager, Bridge Expert, Soils Expert and Pavement Expert on the supervision team. The other four contracts started in April 2001, and Norconsult provided Project Manager, Bridge Expert and Pavement Expert.